“We are pleased to report that we completed the wiring, interconnection of the PLC systems, integration and testing of the first third of the plant, and specifically the robotic loading arms and that the initial tests all resulted in effective and expedient loading of the panels into the system. In fact, the loading systems capacity test exceeded our estimated capacity design maximums by 10 percent,” stated Corrado De Gasperis, chief executive officer of Comstock. “The team will now stress test the particle size reduction stage of the system and continue forward into our proprietary process integration and testing. We remain on track for stress testing those components over the next two weeks.”
The start-up sequence is largely dictated by the engineering requirements and, to a lesser extent, the responses to continued requests for materials and samples from the growing population of potential offtake customers.
Published July 2026